SHANG Jin-cheng, GOU Rui-feng, LI Bin-bin. SPECIAL TECHNICAL PROBLEMS IN COMMISSIONING OF SHENGSI HVDC PROJECT AND THE IRSOLUTIONS[J]. High voltageapparatus, 2003, (1): 1-3+11.
SHANG Jin-cheng, GOU Rui-feng, LI Bin-bin. SPECIAL TECHNICAL PROBLEMS IN COMMISSIONING OF SHENGSI HVDC PROJECT AND THE IRSOLUTIONS[J]. High voltageapparatus, 2003, (1): 1-3+11.DOI:
the problems of stability of weak power system as DC sys te m urgently shutdown
disturbing the running pole caused by idle pole closing no l oad convertor transformer and erroneous firing of convertor valves
which occur red in commissioning of Shengsi HVDC project with weak receiving terminal
are an alyzed and discussed.The solutions are introduced as well.Revealment of these pr oblems will be valuable references to future HVDC projects made domestically.