HE Shan-qing. ANALYSIS ON THE FLASHOVER OF BASIN-INSULATOR IN 550 kV GIS[J]. High voltageapparatus, 2003, (3): 79-80.DOI:
ANALYSIS ON THE FLASHOVER OF BASIN-INSULATOR IN 550 kV GIS
摘要
当大朝山电站1
#
发电机投入试运行时
大昆2
#
线及500 kV系统已空载稳定运行了近两天
调试CAT时
突然因接地故障保护装置动作
断路器分闸。笔者对闪络事故的原因进行了分析。
Abstract
When the commissioning of No.l Generating Unit at Dachaoshan hydropower station
both 500 kV facilities and the No.2 Dakun transmission line were energized with no-load operation for about 2 days. When testing CAT (Circuit Breaker with Artificial Intelligence Technology)
the circuit breaker was suddenly tripped due to earthing fault The cause of the accident is investigated and presented in this paper.