浏览全部资源
扫码关注微信
福建省龙岩电业局,福建,龙岩,364000
Published:2004
移动端阅览
[1]黄炳洪.一起主变有载分接开关油位异常的分析与处理[J].高压电器,2004(02):158-159.
HUANG Bing-hong. Analysis and Treatment of Abnormal Oil Level in OLTC of a Main Transformer[J]. High voltageapparatus, 2004, (2): 158-159.
[1]黄炳洪.一起主变有载分接开关油位异常的分析与处理[J].高压电器,2004(02):158-159. DOI:
HUANG Bing-hong. Analysis and Treatment of Abnormal Oil Level in OLTC of a Main Transformer[J]. High voltageapparatus, 2004, (2): 158-159. DOI:
阐述了主变有载分接开关切换开关油室密封性能的重要性
结合一台220kV主变有载分接开关油渗漏的发现、分析和处理
介绍了消除缺陷的方法。
The importance of oil sealing in OLTC of main transformer is emphasized. With the finding
analysing and treatment of oil-leakage for a 220 kV main transformer’s OLTC
the way to eliminate the defects is introduced.