WANG Ying-jie, LI Bin, TIAN Fang. Gaoling Back to Back Project Thyristor Valve Electrical Design[J]. High voltageapparatus, 2011, 47(6): 34-38. DOI: 10.13296/j.1001-1609.hva.2011.06.008.
Gaoling Back to Back Project Thyristor Valve Electrical Design
摘要
高压直流背靠背工程的主要用途就是使不同电压等级和频率的两大交流系统联网
其中换流阀是换流站中的主要设备
它的作用是把交流电力变换成直流电力
或者实现逆变换。针对高岭背靠背工程±125 kV换流阀电气设计主参数要求
依据换流阀技术规范
通过模拟仿真分析计算
优化了的晶闸管参数
计算出单阀晶闸管串联数、阻尼电阻、阻尼电容、直流电阻以及晶闸管级保护触发电压值等主要电气设计数据
说明设计思路及计算方法的正确性。
Abstract
The main purpose of HVDC back to back project is to unite two large AC power grid of different voltage grade or different frequency.Thyristor valve is the important equipment in the converter station.The purpose of thyristor valve is to use rectifier valve make AC power into DC power
and use inverter valve make DC power into AC power.In allusion to main parameter requirement of Gaoling±125 kV HVDC back to back thyristor valve electrical design
according to thyristor valve design technical specification
use simulate and analysis calculation
optimize the main parameter of the thyristor
and carry out calculation the number of thyristor positions and damping circuit parameters(including damping capacitance
damping resistance and DC resistance)
and coordination of protective firing level.Calculation result verifies the correctness of electrical design.