YAN Qun-min~1, MA Yong-xiang~1, LIU Zhong-wei~2. Analysis of Starting of 750 kV Substation System and Security Precautions[J]. High voltageapparatus, 2012, 48(10): 110-113+119.
YAN Qun-min~1, MA Yong-xiang~1, LIU Zhong-wei~2. Analysis of Starting of 750 kV Substation System and Security Precautions[J]. High voltageapparatus, 2012, 48(10): 110-113+119. DOI: 10.13296/j.1001-1609.hva.2012.10.021.
Analysis of Starting of 750 kV Substation System and Security Precautions
The starting of EHV power grid is a complex and cautious operation
which decides the security of entire power grid.To work out reasonable and effective starting scheme
this paper introduces the wiring system of a 750 kV substation and its interconnected substations
and comprehensively analyzes the idle line’s closing overvoltage
the collocation of system’s relay protection
and the 750/330 kV electromagnetic loop in the starting phase of the 750 kV substation.Correspondingly
the idle line’s closing overvoltage is restricted
the requirement for setting relay protection in the starting phase is proposed
the effect of electromagnetic loop is reduced by controlling provincial-level section current
and the safety precautions for the starting phase are worked out.This project has been accepted by the State Grid Corporation.This study may provide a reference for further development of intelligent power grids
especially for research on starting of EHV grid systems.