ZHAO Yuan, XU Dangguo, PENG Long, et al. Analysis on Artificial Transient Single-phase Grounding Test for 500 kV Shang- Cheng Line Ⅲ with Fixed Series Compensator[J]. High voltageapparatus, 2015, 51(5): 59-62+70.
ZHAO Yuan, XU Dangguo, PENG Long, et al. Analysis on Artificial Transient Single-phase Grounding Test for 500 kV Shang- Cheng Line Ⅲ with Fixed Series Compensator[J]. High voltageapparatus, 2015, 51(5): 59-62+70. DOI: 10.13296/j.1001-1609.hva.2015.05.011.
Analysis on Artificial Transient Single-phase Grounding Test for 500 kV Shang- Cheng Line Ⅲ with Fixed Series Compensator
Electric Power Research Institute of Jibei Electric Power Company Limited(North China Electric Power Research Institute)conducted artificial transient single-phase grounding test for B-phase of 500 kV Shang-Cheng Line III with fixed series compensator. In this paper
the working principle of the test apparatus and the test methods and results are introduced. And the protection performances for the line and the compensator as well as the secondary arc current are analyzed. The results show that the series compensator achieves correct reaction and successful reclosing
and the circuit breakers on both sides of Shang-Cheng Line III work correctly to make a successful single-phase reclosing.