CHEN Bing, ZHANG Qiang. Optimization of Reactive Power Control Logic for UHVDC Transmission Project[J]. High voltageapparatus, 2016, 52(8): 20-23+28. DOI: 10.13296/j.1001-1609.hva.2016.08.004.
Optimization of Reactive Power Control Logic for UHVDC Transmission Project
目的是满足换流站的直流系统无功需求、滤除交流侧谐波、保持交流侧母线电压稳定的要求。±800 k V普洱换流站是云广Ⅱ回特高压直流输电工程中的整流站
其直流站控系统中无功控制功能的电压有效性选择逻辑存在缺陷
文中提出了优化的措施
对特高压直流输电工程的可靠运行有着重要意义。
Abstract
The purposes of reactive power control for UHVDC transmission project are to meet DC converter station’s reactive power demand
filter harmonics at AC side
and keep AC side bus voltage stable. The ±800 k V Pu’er converter station is in the Yun-Guang Ⅱ UHVDC transmission project
however a flaw exists in voltage effectiveness selection logic of the reactive power control function of its DC station control system. This paper proposes optimization measures to eliminate this flaw
thus to benefit reliable operation of UHVDC transmission projects.