Feasibility Analysis of Live Working on the Four Circuit Transmission Lines on the Same Tower
Live working is the most direct and effective means for the maintenance of the multiple circuit transmission lines on the same tower
so it is necessary to analyze the feasibility of live working on the four circuit transmission lines on the same tower. In this paper
the 110 kV
220/110 kV and 500/220 kV four circuit transmission lines on the same tower is taken as the research object
and the safety of live line work is evaluated from the risk of live working on typical position and the
field strength of worker. The calculation results show that the risk rate of live working on the wire of 110 kV
220/110 kV four circuit transmission lines on the same straight-line tower is more than 1×10
-5
and the risk rate of live working on the cross arm of 110 kV four circuit transmission lines on the same strain tower is more than 1×10
-5
which do not meet the requirements of regulation. And the risk rate of live working on the wire of 500/220 kV four circuit transmission lines on the same tower is less than 1×10-5
which meets the requirements of regulation. When workers do not wear shielding clothes and live working on the four circuit transmission lines on the same tower
the largest field strength of the human body are in the position of the feet
respectively
10.803
1 482.2 and 2 138 kV/m
what’s more
at least 37.15
39.90 and 42.67 d B shielding clothing can ensure the safety of the workers. In conclusion
when workers in right conductive clothes and can safely live working on the wire of 500/220 kV four circuit transmission lines on the same tower
but there are safety risks involved to which live line work on the wire of 110 kV
220/110 kV four circuit transmission lines on the same straight-line tower and 110 kV four circuit transmission lines on the same strain tower.
Research on Human Digital Twins for Live Working on Transmission Lines Based on Attitude Estimation
Study on the Amplitude and Energy Characteristics of the in and out of Equipotential Pulse Current for 1000 kV Transmission Line Tension Tower Based on HHT
Live Working Insulation Blanket Surface Defect Recognition Based on Improved YOLOv8
Insulation Protection Design of Live working Robot for 10 kV Distribution Power Systems
Feasibility Research of Live Working on 500 kV Compact Line
Related Author
ZHANG Chengwu
XU Jinshuai
WANG Wei
MA Aiqing
WU Tian
SONG Xuan
PENG Yong
QIU Zhonghua
Related Institution
School of Electrical Engineering, Shanghai University of Electric Power
State Grid Sichuan Extra High Voltage Company
China Electric Power Research Institute
Hubei Provincial Engineering Technology Research Center for Power Transmission Line, China Three Gorges University
College of Electrical Engineering & New Energy, China Three Gorges University