ZHANG Saipeng, FENG Shitao, ZHAO Chunming, et al. Study on Reliability of High Voltage Disconnector Based on Weibull Distribution and Monte Carlo Method[J]. High voltageapparatus, 2021, 57(6): 86-93+101.
DOI:
ZHANG Saipeng, FENG Shitao, ZHAO Chunming, et al. Study on Reliability of High Voltage Disconnector Based on Weibull Distribution and Monte Carlo Method[J]. High voltageapparatus, 2021, 57(6): 86-93+101. DOI: 10.13296/j.1001-1609.hva.2021.06.012.
Study on Reliability of High Voltage Disconnector Based on Weibull Distribution and Monte Carlo Method
The reliability of high voltage disconnector plays an important role in the safe and stable operation the power grid.A fault tree model consisting of such five subsystems as body support
drive mechanism
operating mechanism
insulator and conductive circuit is set up.The operating data of certain company’s disconnector at 110 (66) k V and above is taken as the basis
the Weibull distribution parameters estimation based on least square method and average rank method is studied so to master effectively the variation of the failure probability with the operation time.On this basis
the Monte Carlo method is adopted to analyze reliability of the high voltage disconnector.The result shows that the drive mechanism is a weak link that affects the reliable operation of the disconnector.This method can effectively assess the reliable operation time of the high voltage disconnector and provide guidance strategies for the design
manufacture and condition maintenance of the equipment.