Temperature of contact of GIS is the most direct indicator reflecting thermal fault informationof the contact and is necessary to be monitored real time. At present
it is impossible to install the sensor on the contact to monitor the temperature. Therefore
it is proposed in this paper to use the monitoring value of temperature at multiple point of the enclosure and the ambient temperature for inversion calculation of temperature of the contact of GIS. Also
the multiple-point sensors arranged on the enclosure is optimized. First
a temperature-fluid field finite element analysis model of 500 kV disconnector gas compartment is set up
the distribution of temperature field is calculated and the installation position of the sensors on the enclosure is determined. At the same time
the temperature rise test is performed to compare the test and simulation result in order to verify the rationality of the simulation model. Then
the support vector regression is used to train the corresponding relationship between multiple-point temperature of the enclosure
the ambient temperature and the contact temperature. The actual measurement of the multiple-temperature on the enclosure and ambient temperature is used for conversion calculation of contact temperature. It is found by way of comparing the calculated and actually measured result that the average absolute monitoring error is 0.47%. Finally
the optimal placement of the temperature sensor on the enclosure is performed by using the generic algorithm.The number of sensors is reduced from 25 to 5 and the average absolute monitoring error after optimization is 2.07%
which saves the cost and improves the speed of conversion calculation.